The following steps and payment schedules help ensure fixed pricing and make the administration and building process as streamlined as possible. The Stages listed below are an indicative guide only, based on standard designs, vacant blocks and are subject to all statutory approvals. Long Island Homes will endeavour to progress each stage as early as practicable. Payments made in accordance with the schedule below are non-refundable, except where mutually agreed by both parties.

 

 

First Stage Responsibility

Owner/s

Payment of the initial $1,500 per dwelling deposit is NOT refundable once we have performed drafting or booked the soil report or any other documentation -Multi dwelling projects will be a minimum of $2,500 per dwelling and is Non- Refundable. Initial deposit amount will be deducted from balance of 5% deposit, which will be invoiced after contract signing.

Builder

Explain the different process of a Fixed and Non Fixed Price Contract (please note all Fixed Price Contracts incur a further $1500 non – refundable deposit prior to Colour Selection Appointment)

Owner/s

Decision on a Fixed or Non Fixed Contract process

Owner/s

Supply a clear and legible copy of your Land Contract of Sale, including Title, Section 32,

Section 173, Planning Guidelines and Restrictions, Developer’s Guidelines and

Memorandum of Common Provisions (whichever are applicable).

Owner/s

Advise on lending institution or financial arrangements for funding of construction. Cash

arrangement will require a signed confirmation that payments are the clients full responsibility

Builder

Advise on the positioning of the house on the land that meets compliance with all Covenants and guidelines relating to the land (siting)

Owner/s

Provide a list of variations (additions and extras to the standard house plans and specifications). Please be aware that a $1000 Design fee will be charged PER SKETCH after the 3rd sketch has been completed.

Builder

Preparation of the HIA (Housing Industry Association) Building Contracts and Contract Drawings – there are 3 copies of the contracts and house drawings. 1 for the owner, 1 for the financier and 1 for the builder

Builder and Owner/s

Presentation and acceptance of the Building Contract and Contract Drawings

Owner/s

Once finance is unconditionally approved the owner must supply this letter to the builder

Second Stage :

Builder

If land is titled – Organise a soil test and topographic survey for preliminary foundation assessment. If titles are not released a soil test will be completed in accordance with developers permission

Builder

Order Preliminary Information (Planning Certificates, Sewer and Stormwater

Documentation, Termite Zoning, Bushfire Protection, Flooding, Overland Drainage)

 Builder and Owner/s

The Colour Appointment will be organised by the Interior Designer. Please allow up to 3 hours for this appointment)

Owner/s

Provide land ownership confirmation (Letter of Settlement from Conveyancer or Solicitor)

and Construction Funding confirmation (i.e. Bank Letter of Offer or similar)

  

Third Stage :

Builder and Owner

Pre Site Meeting – This meeting is extremely important to both parties as it is the final check list of all documentation prior to building commencement. The following documentation will be supplied to the client to check and sign off:

  • Complete set of working drawings, including cabinetry, elevations, lighting
  • Complete set of inclusions
  • Colour Selections
  • Pre-site Check List

Builder and Owner’s

All documentation will be presented to client for sign off at the Pre Site meeting

Builder

Apply for the Building permit (Note that any applicable Planning Permits are the responsibility of the Owner/s unless authorised by LIH’s). Payment of Building Permit, Home Owners Warranty Insurance Charges and Statutory Government Charges

Builder

Complete all Administrative processes

Builder

Ordering of all Materials required for construction and assembly of a Site File for the Building Supervisor

Builder

Checking of the Site File and allocation of the Site File to the Building Supervisor. (Note:

Construction of all homes must commence within 21 days of receipt of all the necessary approvals, consents and Building Permit.

Builder and Owner

Progress Payments (all amounts include GST):

  1. Initial Deposit
  2. Contract Signing 5% of Contract Sum, less payment of Initial Deposit
  3. Base Stage Completion 15% of Contract Sum, in accordance with Contract Documentation
  4. Frame Stage Completion 20% of Contract Sum, in accordance with Contract Documentation
  5. Lockup Completion 30% of Contract Sum, in accordance with Contract Documentation
  6. Fixing Completion 20%, in accordance with Contract Documentation
  7. Settlement 10% of Contract Sum, in accordance with Contract Documentation

 

Note: Any Post Contract Variations or Building Variations are payable after completion of the relevant stage.

The above does not apply in any form to allotments which have existing homes requiring demolition.